Grand Bohemian Lodge Asheville
Supporting reopening readiness after flood remediation and a phased guestroom install.
Grand Bohemian Lodge Asheville underwent a renovation project to reopen the hotel after severe flooding in Western North Carolina. The first floor sustained more than five feet of floodwater, requiring a coordinated recovery effort before the property could return to service.
Over five months and several phases, Hilldrup provided freight coordination, receiving, warehousing, inventory management, delivery, FF&E installation, and project management/coordination. The scope included a partial installation of 50 guestrooms across two buildings, including televisions and headboard walls.
Project Snapshot
CLIENT: Grand Bohemian Lodge Asheville
LOCATION: Asheville, North Carolina
PROPERTY TYPE: Hotel Renovation and Reopening After Flood Damage
SCALE: Partial Installation of 50 Guestrooms Across 2 Buildings
TIMELINE: Five Months, Phased
SERVICES: Freight Coordination | Receiving | Warehousing | Inventory Management | Delivery | FF&E Installation | Project Management

Project Challenge
The project was tied to a grand reopening deadline following major flood damage and remediation work. Installation had to continue while the property remained active with owners, contractors, designers, and other trades all working toward the same date.


A room-by-room installation helped support reopening a landmark hotel after extensive flood damage.
Hilldrup’s Approach
Hilldrup delivered and installed guestroom items on a room-by-room basis to align with the phased schedule. The team worked side by side with the general contractor managing flood remediation after Hurricane Helene, helping keep the installation coordinated as the site progressed through recovery.
Because the project required evening work to meet the reopening timeline, coordination was critical. Hilldrup stayed engaged with the project team throughout the process to support sequencing, delivery timing, and room readiness as the property moved toward completion.
Results
The hotel achieved an on-time reopening. The completed work supported the return of rebuilt public spaces and helped restore the guest experience at a landmark downtown Asheville property.