Grand Bohemian Lodge Asheville

Supporting reopening readiness after flood remediation and a phased guestroom install.

Guestroom at Grand Bohemian Lodge Asheville with upholstered headboard, bedside lighting, and seating area

Grand Bohemian Lodge Asheville underwent a renovation project to reopen the hotel after severe flooding in Western North Carolina. The first floor sustained more than five feet of floodwater, requiring a coordinated recovery effort before the property could return to service.

Over five months and several phases, Hilldrup provided freight coordination, receiving, warehousing, inventory management, delivery, FF&E installation, and project management/coordination. The scope included a partial installation of 50 guestrooms across two buildings, including televisions and headboard walls.

Grand Bohemian Lodge Asheville lounge area with red walls, velvet seating, and decorative antler display.

Project Challenge

The project was tied to a grand reopening deadline following major flood damage and remediation work. Installation had to continue while the property remained active with owners, contractors, designers, and other trades all working toward the same date.

Grand Bohemian Lodge Asheville lobby seating area with carved wood details, fireplace, and chandelier.
Private dining room at Grand Bohemian Lodge Asheville with long wood table, chandelier, and upholstered seating.

A room-by-room installation helped support reopening a landmark hotel after extensive flood damage.

Hilldrup’s Approach

Hilldrup delivered and installed guestroom items on a room-by-room basis to align with the phased schedule. The team worked side by side with the general contractor managing flood remediation after Hurricane Helene, helping keep the installation coordinated as the site progressed through recovery.

Because the project required evening work to meet the reopening timeline, coordination was critical. Hilldrup stayed engaged with the project team throughout the process to support sequencing, delivery timing, and room readiness as the property moved toward completion.

Results

The hotel achieved an on-time reopening. The completed work supported the return of rebuilt public spaces and helped restore the guest experience at a landmark downtown Asheville property.